How Does HOA Architectural Review Affect a Custom Home?

By David K

8 min read

Illustrative 3D render of a white two-story board-and-batten home with a dark shingle roof, brick water table, and small front porch on a lawn, not a Max Built project

If your lot is in a neighborhood with recorded covenants, a homeowners association or its architectural review committee usually has to approve the house before construction starts. That review is separate from the city or county building permit, and passing one does not satisfy the other. Get the declaration, every amendment, and the current design guidelines before you close on the lot. Give them to your architect and builder on day one so the size, setbacks, roof, materials, and colors are designed to the rules instead of revised to them. Then build the review into the design schedule, submit a complete package before the permit set is final, and keep written approval of anything you change later.

Planning a new home? Explore Max Built's custom-home process, then view the craftsmanship in our project portfolio.

Read the covenants and design guidelines before you buy the lot

Many newer neighborhoods around Charlotte are planned communities with a recorded declaration, often called the covenants or CC&Rs. In North Carolina, communities created on or after January 1, 1999 generally fall under the Planned Community Act in Chapter 47F of the General Statutes, and some of its sections also reach older communities. The authority to review a house design usually comes from the declaration itself, which often sets up an architectural review committee or gives that job to the board.

The declaration is only part of the picture. Many communities also publish design guidelines, an application form, a fee or deposit schedule, and construction rules for builders. Newer communities may still have the developer controlling review. Ask for all of it, including every amendment, and make sure you have the current versions. A lot can look perfect on the ground and still be limited by a minimum home size, a required material, or a setback that is stricter than zoning.

This belongs in lot due diligence, alongside the survey, soils, utilities, and grading covered in our guide to choosing a custom-home lot. If anything in the documents is unclear, or you are unsure how a restriction applies to your plans, ask a real estate attorney before you close.

What architectural review usually covers

Every community writes its own rules, so treat this as a checklist of what to look for rather than what you will find. Some neighborhoods regulate only a few items. Others publish detailed guidelines that read like a design brief.

The rules that affect a new home most are usually the ones that shape the plan early: size, placement, height, and the exterior palette. Those are cheap to design around in a first sketch and expensive to fix after construction drawings are done. If your community controls exterior materials and colors, our guide to choosing exterior materials can help you build a palette that suits the house and the review at the same time.

  • Minimum heated square footage, number of stories, or maximum height
  • Building setbacks, build-to lines, or lot coverage that differ from zoning
  • Garage location and orientation, and the number of garage bays
  • Roof pitch, roof material, and roof color
  • Exterior materials, masonry requirements, siding types, trim, and paint colors
  • Window, door, and exterior lighting styles
  • Fences, walls, pools, outbuildings, and accessory structures
  • Landscaping plans, tree removal, and grading or drainage changes
  • Location of equipment such as HVAC units, generators, and trash areas
Illustrative 3D render of exterior material samples on a wood table: white board-and-batten and lap siding, red and white brick, stone, a shingle sample, a dark standing-seam metal piece, trim, and paint chips
Illustrative render. Many review committees ask to see actual material and color samples, not just names on a list.

Build the review into the design schedule

Architectural review takes time, and the timeline comes from the community's documents, not from a single statewide rule. Some committees meet on a set calendar. Some offer a preliminary review of a concept before a final submittal. Some may require approval before a lot is cleared. Find out the meeting dates, the expected response time, and what happens if the committee asks for changes, and get those answers in writing.

A practical sequence is to share the documents with your architect and builder before the first concept, ask for an informal or preliminary review once the site plan and elevations are taking shape, and submit the final package before the permit drawings are locked. That order keeps one set of drawings moving forward instead of two versions that drift apart. It also gives you room to settle questions about materials and colors before anything long-lead is ordered.

It helps to agree early on who manages the submittal. On many custom homes the builder or architect prepares the package, but the owner signs the application and receives the decision. Decide who tracks comments and keeps the approved set.

Put together a complete submittal package

An incomplete application can mean a second round of review, so read the application checklist carefully and match it item by item. Most of what a committee wants overlaps with drawings the project already needs, especially a clear site plan. Our guide to what a custom-home site plan should show explains how to build one current base that serves every review.

Label materials and colors the same way on every drawing and sample. If the guidelines allow an alternate, show it and ask for approval of both so a later supply problem does not send you back to the committee.

  • Site plan showing property lines, setbacks, easements, the house footprint, the driveway and walks, and any pool, fence, or outbuilding
  • Exterior elevations of every side of the house, with heights shown
  • Floor plans and a roof plan with pitches
  • A schedule of exterior materials and colors, with samples if requested
  • Landscape plan, tree removal plan, and grading or drainage information if required
  • Exterior lighting, fencing, and equipment locations
  • The application form, any fee or deposit, and the builder's information if required
Illustrative 3D render of a site plan drawing on a table showing a dashed property line, setback lines, a house footprint, a front walk, and trees, with rolled plans beside it
Illustrative render. A clear site plan with property lines and setbacks is usually the core of the submittal.

HOA approval and the building permit are separate

A building permit shows the house meets the building code and local zoning. It does not show the house meets private covenants. Approval from the committee does not replace a permit, inspections, or zoning review either. The Planned Community Act itself says it does not change local zoning, subdivision rules, or building codes. You need both approvals, and the drawings for each should describe the same house.

Keep the two sets matched. If plan review requires a change that affects the exterior, such as a revised window, a different roofline, or a moved footprint, check whether the committee needs to see it. Our permit set checklist covers how to manage revisions so every reviewer is looking at the current drawings.

Expect rules for the construction itself

Many communities set rules for how the home is built, not only how it looks. Common examples include a construction deposit, working hours, where workers park, silt fence and erosion control, dumpster and portable toilet placement, keeping streets and common areas clean, and a deadline to finish once work starts. Read these before construction pricing is final so the builder can plan for them.

Under the Planned Community Act, an association can fine owners for violations of its declaration, bylaws, and rules only after notice and an opportunity to be heard. The better goal is to avoid the dispute entirely. Keep the approval letter on site, build to the approved drawings, and ask before changing anything the committee approved.

Solar panels have their own rule in North Carolina

If you want solar now or later, know that North Carolina law limits how far covenants can go. Under N.C. Gen. Stat. § 22B-20, a covenant that would prohibit, or have the effect of prohibiting, solar collectors on a residential property is generally void. A covenant may still regulate where collectors go and how they are screened, as long as it does not prevent reasonable use, and it may bar certain visible locations, such as a roof slope facing a street or common area. The Supreme Court of North Carolina applied the statute in a 2022 case involving an architectural committee.

For a new home, the practical move is to design for it. Give the architect the community's solar rules and plan a roof plane that works for panels without facing the street, if the site allows. Our guide on making a custom home solar-ready covers the wiring and roof planning to do during construction.

Questions to settle before the plans are final

If you are planning a new home in the Charlotte area on a lot with HOA review, it is easier to design to the rules from the start than to redesign later. See how the custom-home process works, look through our portfolio, or contact Max Built to talk through your lot and plans.

  • Do we have the recorded declaration, every amendment, and the current design guidelines?
  • Who reviews plans now: a committee, the board, or the developer?
  • Does the community offer a preliminary review, and when does the committee meet?
  • Which rules limit size, height, setbacks, garage placement, or materials on this lot?
  • What does the application require, and is there a fee or construction deposit?
  • Who prepares the submittal, and who keeps the approved drawings?
  • What construction rules apply to working hours, parking, cleanup, and completion?
  • If something changes after approval, what needs to be resubmitted?

Sources and editorial notes

North Carolina General Statutes, Chapter 47F, North Carolina Planned Community Act (PDF)

N.C. Gen. Stat. § 47F-3-102, Powers of owners' association

N.C. Gen. Stat. § 22B-20, Deed restrictions and other agreements prohibiting solar collectors

Supreme Court of North Carolina, Belmont Association, Inc. v. Farwig, 2022-NCSC-64 (PDF)

Prepared with AI assistance and editorially reviewed by Grok/AI. Architectural images are illustrative, not documented Max Built projects. This organizational guide does not replace project-specific professional advice.

Frequently asked questions

HOA review questions for new custom homes

Does HOA approval replace the building permit?

No. HOA or architectural committee approval and the building permit are separate. The permit covers building code and local zoning, while the committee reviews the home against the community's private covenants and guidelines. Most homes in these communities need both before construction begins.

When should I submit plans to the architectural review committee?

Check your community's guidelines, because the process varies. In general, share the documents with your architect and builder before design starts, ask for a preliminary review if one is offered, and submit the final package before your permit drawings are locked and before long-lead exterior materials are ordered.

Can an HOA in North Carolina ban solar panels on a new home?

Generally not outright. Under N.C. Gen. Stat. § 22B-20, covenants that prohibit or effectively prohibit residential solar collectors are generally void. Communities can still regulate location and screening as long as reasonable use remains possible, and they can restrict certain locations visible from streets or common areas. Read your community's rules and plan the roof with them in mind.

What happens if I change an approved exterior material during construction?

Ask the committee before you make the change. Many communities require approval for changes to approved materials, colors, or drawings. Get any approval in writing and keep it with the approved plans.

Where do I get the covenants for a lot?

Covenants are usually recorded with the county register of deeds, and the association or its management company can often provide the current declaration, amendments, design guidelines, and application forms. A real estate attorney can review them with you before you close on the lot.

Start the conversation

Build the right plan before construction begins

Tell us about your property, priorities, and the way you want to live. We'll help organize the next decisions around a clear, buildable path.

Trusted by Charlotte homeowners

5.0

Average client rating · 28 reviews

Custom home

Max Built built our home in Weddington and stayed on budget the entire way through. Our project lead was on site every week and picked up the phone when we called.

Sarah T.

Weddington, NC

Whole home renovation

We did a whole home renovation in Myers Park. They treated it like new construction, not a patch job. Inspections passed clean at every stage.

Michael R.

Myers Park

Custom home

Honest numbers from day one. When we changed cabinet selections mid build, they showed us the cost in writing before anything moved forward.